§ 197.530 Correction program; procedures.
Oregon Revised Statutes ORS chapter 197
ORS sections in this chapter were amended or repealed by the Legislative Assembly during its 2026 regular session. See the table of ORS sections amended or repealed during the 2026 regular session: 2026 A&R Tables
New sections of law were added by legislative action to this ORS chapter or to a series within this ORS chapter by the Legislative Assembly during its 2026 regular session. See sections in the following 2026 Oregon Laws chapters: 2026 Session Laws 0089
A city, county or special district that adopts a moratorium on construction or land development in conformity with ORS 197.520 (1) and (2) shall within 60 days after the effective date of the moratorium adopt a program to correct the problem creating the moratorium. The program shall be presented at a public hearing. The city, county or special district shall give at least 14 days’ advance notice to the Department of Land Conservation and Development of the time and date of the public hearing.
No moratorium adopted under ORS 197.520 (2) shall be effective for a period longer than six months from the date on which the corrective program is adopted, but such a moratorium may be extended provided the city, county or special district adopting the moratorium holds a public hearing on the proposed extension and adopts written findings that:
Verify that the problem giving rise to the moratorium still exists;
Demonstrate that reasonable progress is being made to alleviate the problem giving rise to the moratorium; and
Set a specific duration for the renewal of the moratorium.
No single extension under subsection (2) of this section may be for a period longer than six months, and no moratorium shall be extended more than three times.
Any city, county or special district considering an extension of a moratorium shall give the department at least 14 days’ notice of the time and date of the public hearing on the extension.
[1980 c.2 §4; 1991 c.839 §4]