§ 215.276 Required consultation for transmission lines to be located on high-value farmland.

Oregon Revised Statutes ORS chapter 215

Later legislation

ORS sections in this chapter were amended or repealed by the Legislative Assembly during its 2026 regular session. See the table of ORS sections amended or repealed during the 2026 regular session: 2026 A&R Tables

New sections of law were added by legislative action to this ORS chapter or to a series within this ORS chapter by the Legislative Assembly during its 2026 regular session. See sections in the following 2026 Oregon Laws chapters: 2026 Session Laws 0123

(1)

As used in this section:

(a)

“Consult” means to make an effort to contact for purpose of notifying the record owner of the opportunity to meet.

(b)

“High-value farmland” has the meaning given that term in ORS 195.300.

(c)

“Transmission line” means a linear utility facility by which a utility provider transfers the utility product in bulk from a point of origin or generation, or between transfer stations, to the point at which the utility product is transferred to distribution lines for delivery to end users.

(2)

If the criteria described in ORS 215.275 for siting a utility facility on land zoned for exclusive farm use are met for a utility facility that is a transmission line, or if the criteria described in ORS 215.274 for siting an associated transmission line are met, the utility provider shall, after the route is approved by the siting authorities and before construction of the transmission line begins, consult the record owner of high-value farmland in the planned route for the purpose of locating and constructing the transmission line in a manner that minimizes the impact on farming operations on high-value farmland. If the record owner does not respond within two weeks after the first documented effort to consult the record owner, the utility provider shall notify the record owner by certified mail of the opportunity to consult. If the record owner does not respond within two weeks after the certified mail is sent, the utility provider has satisfied the provider’s obligation to consult.

(3)

The requirement to consult under this section is in addition to and not in lieu of any other legally required consultation process.

[2009 c.854 §1; 2013 c.242 §7]

Legislative Counsel’s note

Note: 215.276 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 215 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.