§ 215.447 Photovoltaic solar power generation facilities on high-value farmland.
Oregon Revised Statutes ORS chapter 215
ORS sections in this chapter were amended or repealed by the Legislative Assembly during its 2026 regular session. See the table of ORS sections amended or repealed during the 2026 regular session: 2026 A&R Tables
New sections of law were added by legislative action to this ORS chapter or to a series within this ORS chapter by the Legislative Assembly during its 2026 regular session. See sections in the following 2026 Oregon Laws chapters: 2026 Session Laws 0123
As used in this section, “photovoltaic solar power generation facility” means an assembly of equipment and components that has the primary purpose of converting sunlight into electricity by photovoltaic effect and has the capability of storing or transferring the electricity.
A photovoltaic solar power generation facility may be established on land that is high-value farmland, as defined in ORS 195.300 (10)(f)(C), provided the land:
Is not located within the boundaries of an irrigation district;
Is not at the time of the facility’s establishment, and was not at any time during the 20 years immediately preceding the facility’s establishment, the place of use of a water right permit, certificate, decree, transfer order or ground water registration authorizing the use of water for the purpose of irrigation;
Is located within the service area of an electric utility described in ORS 469A.052 (2);
Does not exceed the acreage the electric utility reasonably anticipates to be necessary to achieve the applicable renewable portfolio standard described in ORS 469A.052 (3); and
Does not qualify as high-value farmland under any other provision of law.
When evaluating an application to establish a photovoltaic solar power generation facility under this section, a county:
Shall apply the criteria and standards applicable to agricultural land adopted under a statewide land use planning goal relating to agricultural lands; and
May not apply the criteria and standards applicable to high-value farmland adopted under a statewide land use planning goal relating to agricultural lands.
A county is not required to adopt an exception under ORS 197.732 to a statewide land use planning goal relating to agricultural land to authorize the establishment of a photovoltaic solar power generation facility under this section.
[2017 c.504 §2]